Deadline looms large for contractors to finish and hand-over
the Mafikeng Revitalisation road projects by Friday this week.
•
Roads construction companies appointed to rehabilitate five
road projects identified by the Department of Public Works,
Roads and Transport for purposes of assisting in the revitalisation
effort of Mahikeng and Mmabatho, have until Friday this week
to complete the works and hand over the projects to the department.
•
This was an understanding and a commitment by all parties,
following an urgent meeting convened by the MEC for Public
Works, Roads and Transport, Mahlakeng Mahlakeng on Friday,
September 02.
•
The meeting was attended by contractors and representatives
of a firm of consultants appointed to oversee and monitor the
work on our behalf:
•
A directive was issued to all contractors that the remaining
work on all the five road projects ought to complete and handed
over to the department by Friday, September 23.
•
We are pleased that at least one of the projects, which was
the rehabilitation of a portion of the N18- from Mahikeng to
Magogoe Bridge- by the company, M Civil (Pty) Ltd, was completed
even before an ultimatum was issued.
•
It is also important to emphasise the point that this project
was two months ahead of schedule and a decision was taken to
open road for traffic, even though it yet to be open officially.
•
In view of the ultimatum, and the understanding from the urgent
meeting referred to earlier, we expect Ultrasonic Express;
to hand over a completed 2.1km which includes sections of on
Ngaka Modiri Molema, James Moroka and Sekame roads.
•
The same applies to companies IBD Civils JV Phenno Business
Enterprise and Black Hawk with regards to Onkgopotse Tiro (2.8km);
Joe Slovo and Dorothy streets (2.4km) as well as the 2.1km
on Moshoeshoe and Sekame roads.
Status with regards to the Pilanesberg Airport near Sun City,
Rustenburg.
• The
Department has lodged an application with the South African
Civil Aviation Authority for the operating license
of the Pilanesberg Airport to continue operations at the Pilanesberg
Airport from the 01st October 2011
• The application is subject to a compliance inspection by the
SACAA which is expected to be conducted during October 2011.
• This we did because of our unhappiness with the Airports Company
of South Africa (ACSA) in the manner they communicated their
intention to pull out of Pilanesberg airport.
• In March 2011, Airports Company of South Africa (ACSA), the
current operator at Pilanesberg International Airport, informed
us of their intention to withdraw from the Pilanesberg Airport
from 01 April 2011, citing the fact that they were operating
the facility at a loss.
• We had a meeting with ACSA, following their intention to withdraw,
to discuss a number of issues, which included:
The strategy and the plan to withdraw; the request to remain
for a period of six (06) months so that the Department could
prepare itself.
• We also wrote to ACSA requesting them to stay for six months
until the department is ready to take over the facility, and
this proposal was agreed to by ACSA.
• The rationale for the above was also based on the fact that
the withdrawal by ACSA as from April 01 this year, was at short
notice, as it was already the last week of March.
• The two legal teams were the first to meet. The outcome of
the legal teams in terms of investigating/material conditions
for the withdrawal with respect to the contract revealed confirmed
that a twelve (12) months notice should be given in writing
by the tenant and that the contract was in 1998 for 25 years
and it is left with 13 years to expire
• ACSA refused to accept the outcome mentioned above, since they
were already a month into the extension.
• They further requested the department to pay them R500, 000.00
per month for their stay at Pilanesburg Airport.
• We informed ACSA that they needed to give twelve months written
notice to the department of their intention to withdraw from
Pilanesburg Airport.
• ACSA however wanted the department to enter into a contract
with them for the six months they were requested to stay, with
a financial implication of more than half a million.
• This was not possible, as their current contract is still valid.
ACSA then applied to the South African Civil Aviation Authority
(SACAA), to suspend the Operating Licence of Pilanesburg Airport
as at the end of July 2011. This would mean that the airport
would be closed for operations as it would have no operating
license.
•
Concern over the poor response to renew lease agreements by
NW public servants occupying state houses and flats.
• We
have noted with concern the poor response by public servants
occupying state houses and flats in Mahikeng and Mmabatho,
to our plea to come forward and renew lease agreements before
end of August.
• Only 77 of the 224 occupants of state houses and flats in Mahikeng
and Mmabatho have renewed lease agreements to date, and 147
are still outstanding according to our records.
• The demand for state residential accommodation in Mahikeng
and Mmabatho is very high, with 38 applicants- all senior officials
in government- who are yet to be allocated state residential
accommodation.
• There are 220 from levels of deputy director downwards, also
on the waiting list to date.
• Surely we have a duty as a department to find accommodation
for them, in as much as we have a responsibility to also evict
from state properties; those who continue defy orders and or
refuse to be compliant.
END